Port of London Authority

River Works Licence Applications Received

Current list of River Works Licence applications received

Last update - 05/08/2010

PLA Ref No. Location Description of proposed works Date received Status Decision
AN/30/472 Lee Tunnel Outfall culvert 21/05/08 In progress  
AN/14/347 Watermans Quay, Fulham Riverwall repairs 22/09/08 In progress  
AS/33/18 Mulberry Wharf demo 2 mooring piles & pipeline 22/08/08 In progress  
AN/02/46-7 Twickenham Emb. Install fenders 02/09/08 In progress  
AN/01/10 99 Strawberry Vale, Twickenham Pontoon,brow & 2x piles  0809/08 In progress  
A2/20/2 Blackfriars Bridge Extension monitoring 10/09/08 Consent granted  
A2/40/36 Denton, Gravesend 2 mooring piles 12/09/08 In progress  
AN/79/42 Kingsbridge Whf,Barking Creek Remedial works 08/09/08  In progress  
 AS/07/25  Kew embankment  Remedial works  03/12/08 In progress  
AN/30/467 Gallions Point, Lead In Jetty jetty head & extension 19/11/08 In progress  
AS/15/101 & AS/30/101 Barnes - Beckton ST Works Boreholes 10/12/08 In progress  
A2/09/1 Barnes Railway Bridge Scaffold 18/12/08 In progress  
A2/83/36 Holehaven new works - mooring 14/01/09 In progress  
AS/33/20 Church Manorway, Erith jetties, moorings, piles & ramp 24/01/09 In progress  
AEP/02/5 Eel Pie Island, Twickenham 2 mooring posts 26/01/09 In progress  
AS/22/208 Unity Wharf 3 overhanging balconies (crane & lockum) 03/02/09 In progress  

AS/33/25

Erith construction of new steel jetty 10/02/09

In progress

 

AN/34/76-7 Mar Dyke, Purfleet public foot & cycle path bridge 25/02/09 Consent granted  
A2/43/126 Shellhaven install 20 piezometers 06/03/09 Consent granted  
AS/14/121-122 Oyster Wharf, Battersea install piles, pontoon & access bridge 20/03/09 In progress  
AN/35/84 Purfleet Pier jetty & various other works 11/03/09 In progress  
AS/29/517 Woolwich Woolwich free ferry 08/04/09 In progress  
AS/39/104-112 Bevans Wharf, Northfleet demolition of jetty crane & 3 chimneys 06/02/09 Consent granted  
AN/23/204-7 Metropolitan Wharf, Wapping Platform & loading lophole platforms 18/02/09 In progress  
AN/23/223 Phoenix Wharf balconies 27/04/09 In progress  
AS/76/17&18 46&47 49&51 AS/79/13 Deptford Creek flood defence repairs to 7 frontages/river walls 22/04/09 In progress  
AN/10/271 London, W6 2 moorings 05/05/09 In progress  
A2/20/2 Blackfriars repair, widen, & strengthen rail bridge 20/05/09 In progress  
A2/83/36 Holehaven Creek mooring no. 118 01/06/09 Consent granted  
A2/83/36 Holehaven Creek mooring no. 124 04/06/09 Consent granted  
AN/02/59 Twickenham steel pontoon, cone top & catwalk 08/06/09 In progress  
AS/76/28-29 & AS/76/30-31 Sun Wharf & Theatre Wharf repair of river wall 08/06/09 In progress  
AN/4/114A Isleworth barge grid 13/06/09 In progress  
AS/38/95 Britannia Refined Metals Wharf 9 piles & sheet piling 11/06/09 Consent granted  
AN/11/304-7 Thames Wharf & Palace Wharf flood defence repairs 03/07/09 In progress  
AS/15/146-7 Albion Riverside (Coupers Quay) moorings, gangways & walkways for barges 21/07/09 In progress  
AS/40/164 Gordon Promenade, Gravesend beach shingle replenishment 31/07/09 In progress  
 AN/14/344B Fulham Wharf pipes, concrete apron & pile supports  01/04/09  In progress  
 AS/15/130 Valiant House, Wandsworth removal of vegetation and repair marine wall  03/08/09  In progress  
AS/27/445-451 Syral UK, Greenwich demolition of silos & jetty 14/09/09 In progress  
AN/32/46A & AN/32/40A Dagenham pumping stations 03/09/09 Consent granted  
AN/06/148 & AN/06/150B Soaphouse Creek & River Brent, Brentford installation of leisure and commercial moorings 15/10/09 Consent granted  
AN/14/344A & AS/13/103 Wimbledon to Kensal Green Construction of cable tunnel 04/11/09 Consent granted  
AS/40/145 Town Pier, Gravesend Installation of pontoon 03/11/09 Consent granted  
A2/85/22 Benfleet Creek installation of new mooring 07/11/09 In progress    
AN/79/7, AN/31/33A & AN/32/49 Oakentrough & Whitings Sluice, Barking - Buzzards Creek - Havering Sluice Refurbishment to tidal sluices 12/11/09 Consent granted    
AS/10/57 Londsdale Road, London SW1 refurb & redev and proposed new outfall 25/11/09 In progress    
AS/81/35 - AS/81/40A Dartford Creek realignment of flood wall and construction of new new walkway 25/11/09 In progress    
AN/15/361 Lots Road masonry replacement & repointing of river wall 09/12/09

Consent granted

 

   
AN/44/137 Canvey Island maintenance repairs & strengthening of Oikos Jetty No. 1 09/12/09 Consent granted    
 AN/79/42-3 Kingsbridge Ind. Est. Barking extended works to frontages  02/12/09 Consent granted    
 AN/78/23  Orchard Wharf  flood defence improvements  01/12/09  Consent granted    
 AN/02/69A  Twickenham change of use to Passenger Pier  03/02/10  Consent granted    
AS/03/08 Twickenham new toilet facilities on pontoon 07/12/09 Consent granted    
AS/34/56A Erith removal of Clubship & installation of pontoon 17/02/10 Consent granted  pontoon installed & ship removed  
AS/33/25 Erith proposed new outfall & stilling basin 24/02/10 Consent granted    
AN/76/36-50 Deptford Creek various works 03/02/10 In progress    
AS/27/441 Pipers Barge Road screw to be placed to lower end of mooring 04/03/10 Consent granted    
AN/85/36 Benfleet Creek houseboat 'Beetroot' 17/02/10 Consent granted    
AN/85/36 Benfleet Creek houseboat 'Altair' 01/02/10 Consent granted    
AN/15/359 Chelsea Harbour houseboat 'Tangoroa' 22/03/10 Consent granted    
AS/40/147 St Andrews Tier, Gravesend Variation - single mooring to 3 point trot mooring 25/03/10 Consent granted    
AS/13/84-85 Wandsworth permanent residential moorings 09/03/10 Consent granted    
AN/06/172-3 Kew Road Bridge, Brentford Surface Water Outfall 09/04/10 Consent granted    
AN/36/87 Purfleet 10 new moorings 12/04/10 Consent granted    
AS/29/489 AS/27/448 & 450 Vaizeys/Morden & Primrose Wharves flood defence repairs & scoping report 26/04/10 In progress    
A2/84/41 East Haven Creek Saline lagoon 20/04/10 Consent granted    
AN/03/104A 8A Ducks Walk, Twickenham Installation of campsheeting & reinforcement of decayed timber piling 28/04/10 Consent granted    
AN/06/79 Barking Creek Construction of site drainage outfall 17/05/10 In progress    
 AS/26/354  Borthwick Street  slipway reinstatement  01/04/10  In progress    
 AN/20/134  Swan Lane Pier  removal of 'Regalia'  10/06/10  Consent granted    
A2/83/36 Holehaven Creek relocation of buoy 17/06/10 Consent granted    
AN/06/172-3 Kew Bridge Road installation of cantilever brow/shallow draft pontoon 12/07/10 Consent granted    
AS/17/36 St George Wharf passenger pier, bankseat, fixed bridge, access brow, pontoon 02/07/10 In progress    
AN/10/276 Hammersmith Boathouse removal of pontoon 16/07/10 Consent granted    
AN/1/9 101 Strawberry Vale, Twickenham removal of works - ladder and runners to remain 09/07/10 In progress    
AS/29/517 Woolwich Free Ferry installation of piled berthing dolphin 10/07/10 In progress    

For more information on any of the river works licence applications listed please contact the Licensing Officer on 01474 562588 or via this Enquiry Form.


PLA, London River House, Royal Pier Road, Gravesend. Kent DA12 2BG Tel. +44 (0) 1474 562200
© 1998-2010 Port of London Authority and MSO.net